Wednesday, April 14, 2010

Outside Painting Completed-Each Floor Walk-way Paint Schedule

The outside painting at the Destin Pelican Beach Resort has been completed. However, the fun is now beginning. Actually what I am talking about is the painting of the walk ways on each floor(in front of the front condo doors).

Joan Neese(With the Pelican Beach Resort homeowners association) has sent each Pelican Beach Resort Condo owner(Pelican Building on the beach) a copy of the schedule for this walkway painting.

April 20, 2010 Floors 15 & 18 (Tuesday)

April 21, 2010 Floors 16 and 20 (Wednesday)

April 22, 2010 Floors 14 & 19 (Thursday)

April 24, 2010 Floors 1 & 2 (Saturday)

April 26, 2010 Floors 3 & 4 (Monday)

April 27, 2010 Floors 6 & 7 (Tuesday)

April 28, 2010 Floors 9 & 12 (Wednesday)

April 29, 2010 Floors 8 & 11 (Thursday)

April 30, 2010 Floor 17 (Friday)

May 1, 2010 Floors 5 & 10 (Saturday)



In the event of a rain day the floors that would have been painted on that day will be pushed until the end of the project instead of disrupting the rest of the schedule.

This schedule indicates the dates each floor will be closed for painting. If the floor where you are scheduled to be is indeed closed, the Pelican Beach Resort staff will move those renters to another floor temporarily until the paint is dry.

Joan told me that since my floor(10th) is projected to be closed(unless it is rainy that day)May 1st, my renter can check in at 4pm on May 2nd. Actually my calendar is open for May 1st so my renter will not have to be relocated temporarily.

I appreciate all the support my readers are giving me and I also appreciate all the renters of my Pelican Beach Resort condo on the beach.

No comments:

Post a Comment